Outcome
Phase two connected into existing infrastructure without redesign, which was the test the master plan was built to pass.
- Planned area
- 85,000 m²
- Phases
- 3 blocks
- Built to date
- 2 phases
- Shared infrastructure
- Sized once for 8.5 ha
Because the reservoir, pump station and packhouse were positioned for the final area before phase one, phase two required no relocation of shared infrastructure and no rework of the main irrigation network.
Setting gutter direction from the site survey allowed drain water to be collected by gravity across all blocks, removing a pumping station that had been assumed in the original concept.
Insect exclusion measures specified at design stage reduced the pest pressure inherited from adjacent open field production and supported the residue compliance the export buyers required.