How Much Does A Commercial Greenhouse Cost

Commercial greenhouse cost benchmarks per square metre and per hectare, covering structure, climate systems, irrigation and civil works, plus the exclusions that inflate final budgets.

By Aegis Investment Advisory

Published /Updated

Large multi-hectare commercial glass greenhouse complex at dusk, its glazed facade and gutter line receding into the distance

The short answer

A commercial greenhouse typically costs between €35 and €260 per square metre installed, which is €350,000 to €2.6 million per hectare. The spread is wide because the phrase "commercial greenhouse" covers everything from a passively ventilated film structure to a semi-closed glass facility with combined heat and power. The number that matters is not the square-metre price but the total delivered cost of a facility capable of producing your target crop in your climate.

Cost by technology band

Capital cost is driven primarily by glazing and climate control, not by span width or aesthetics. Each band below assumes a complete installed facility including structure, glazing, basic irrigation and climate control, but excluding land and civil works.

  • Multi span film, passive ventilation: €35 – €60 /m²
  • Multi span film with heating and screens: €60 – €95 /m²
  • Multi span polycarbonate: €90 – €130 /m²
  • Venlo single glass with active climate: €120 – €180 /m²
  • Venlo double glass, cold climate package: €170 – €220 /m²
  • Semi-closed glass with cooling: €200 – €260 /m²

How the budget breaks down

Buyers frequently assume the structure dominates the budget. In a fully equipped facility it is usually less than half. Climate and irrigation systems, which determine whether the crop performs, account for a larger share than most first-time investors expect.

The exclusions that break budgets

The most common cause of a greenhouse project running over budget is not price escalation. It is scope that was never quoted. Supplier offers are frequently ex-works and structure-only, while the client assumes an installed and operational facility.

  • Civil works, site levelling and drainage: 5 – 15% of capex
  • Water treatment and storage: 4 – 8%
  • Energy and humidity screens: 6 – 10%
  • Installation supervision and commissioning: 2 – 4%
  • Import duties, inland freight and insurance: 3 – 8%
  • Spare parts and first-season support: 1 – 3%

Why cost per kilogram matters more

Two facilities at the same square-metre price can differ by 30 percent in energy consumption. Since energy is typically the largest operating cost in a heated greenhouse, the cheaper structure often produces the more expensive kilogram. Comparing offers on capital cost alone systematically favours the specification that will cost more to run for the next twenty years.

How to get a number you can rely on

A defensible budget requires a written specification before any quote is requested. Once scope is fixed in a single document, supplier offers become comparable and the levelled total is usually within a few percent of the final delivered cost. Without that document, early estimates should be treated as indicative only.

Indicative capital breakdown for a fully equipped 5 hectare glass facility
Cost componentShare of capexNotes
Structure and glazing38 – 45%Frame, foundations, glazing, ventilation
Climate systems18 – 25%Heating, screens, control computer, CO₂
Irrigation and fertigation8 – 12%Head station, dripline, recirculation
Growing system5 – 9%Gutters, substrate, crop support
Civil works5 – 15%Levelling, drainage, roads, concrete
Water treatment and storage4 – 8%Filtration, RO where required, basins
Engineering and supervision3 – 6%Specification, tender, site supervision

About the author

Aegis Investment Advisory

Feasibility and capital planning desk

The advisory desk builds the feasibility and capital models that Aegis clients present to boards and lenders. Work focuses on cost per square metre, energy cost per kilogram, phased capital deployment and the assumptions that determine whether a project is financeable.

  • Feasibility modelling
  • Capital planning
  • Energy economics
  • Risk assessment

FAQ

Frequently asked questions

How much does a 1 hectare commercial greenhouse cost?

Between roughly €350,000 for a passively ventilated film structure and €2.6 million for a semi-closed glass facility with full climate control. For a year-round heated glass vegetable facility, €1.2 to €1.8 million per hectare installed is a realistic planning figure before civil works and land.

Why do supplier quotes for the same greenhouse differ so much?

Almost always because the scopes differ. One offer may be ex-works structure only while another includes installation, screens, irrigation and commissioning. Until every offer is levelled to identical scope, the price differences are not comparable and the lowest number is usually the least complete.

Is a cheaper greenhouse ever the better investment?

Yes, when the crop and climate do not require the additional technology. Strawberry in a mild climate rarely justifies glass. But in a cold climate growing year-round tomato, cutting the screen package to reduce capital cost raises energy cost per kilogram for the life of the facility.

How much should we budget for engineering and supervision?

Three to six percent of capital cost. It is the line item most often cut and the one that most reliably pays for itself, because it is what makes supplier offers comparable and performance criteria enforceable.