| 1. Foundations, anchors and drainage |
A Venlo glass structure and a Gothic multi-span frame can have different column reactions, gutter elevations and anchor-bolt templates. Confirm design wind and snow loads in kN/m², finished floor levels and drainage falls. |
Foundation-reaction schedule, anchor layout, civil tolerances and drainage drawing. |
| 2. Erection and site logistics |
4 m to 6 m structural bays, glazing packs and roof-vent components may require defined lifting access, laydown space and temporary works. “Supply only” is not equivalent to installed alignment. |
Erection method statement boundary, crane assumptions, unloading plan and site-access requirements. |
| 3. Cladding and energy screens |
Check whether 4 mm tempered glass, diffuse film, screen fabric, drives, edge seals and replacement materials are all listed. A woven thermal screen changes night heat loss and humidity management, but requires access for maintenance and screen-gap adjustment. |
Cladding specification, screen layout, drive schedule, light-transmission data and replacement-scope statement. |
| 4. Heating, ventilation and cooling |
A boiler with heat buffer tank, HAF fans, roof-vent drives and 70 bar high-pressure fogging can be quoted as equipment without the pipework, electrical feed, control points or water treatment needed to run them. Heating capacity should be expressed in W/m² against the stated outside design temperature. |
Heat-load basis, hydraulic schematic, electrical load list, ventilation schedule and climate-control point list. |
| 5. Irrigation, fertigation and treatment |
A 4 L/h drip emitter, EC/pH dosing controller, filtration skid and UV unit are not interchangeable line items. Flow, pressure, water chemistry, drainage recovery and crop substrate determine whether the system can be commissioned as quoted. |
Water analysis, irrigation-zone flow calculation, filtration specification, fertigation P&ID and commissioning responsibility. |
| 6. Incoming utilities and connections |
Incoming electricity, gas, water, communications and discharge connections sit outside many equipment offers. A 400 V supply, available kVA capacity, water pressure and connection date must be confirmed rather than assumed. |
Utility data sheet, metering boundary, connection drawings and written confirmation of available capacity. Use the commercial greenhouse utility planning guide where these interfaces remain unresolved. |
| 7. Controls, alarms and remote access |
A Priva or HortiMaX climate computer is only integrated when the I/O schedule, sensor ownership, protocol licences, alarm routing and remote-access permissions are defined. A listed controller without tested signals to pumps, vents and heating valves is incomplete. |
Controls architecture, I/O list, network diagram, alarm-test script and operator-access schedule. |
| 8. Commissioning and calibration |
Delivery does not demonstrate operation. Specify functional tests for temperature sensors, RH sensors, irrigation-zone pressure, vent position feedback and alarm escalation; for example, climate setpoints such as 18°C night operation must be demonstrably achieved under agreed test conditions. |
Commissioning plan, calibration records, test forms, acceptance criteria and training agenda. |
| 9. Warranty, spares and service access |
Screen gearmotors, inflation fans, filters, emitters and pH probes have different wear and replacement needs. A 12-month equipment warranty may exclude labour, travel, consumables or software support. |
Warranty schedule, response boundary, recommended critical-spares list and maintenance-access drawing. |
| 10. Design assumptions and future interfaces |
Check stated operating inputs, including a winter minimum temperature, CO₂ planning range of 800–1,200 ppm where relevant, water quality and future expansion loads. These inputs affect boiler sizing, dosing capacity, roof-vent control and electrical distribution. |
Assumptions register linked to drawings, equipment capacities and each supplier clarification. |